Sample BOQ in Construction: Real Example with Full Breakdown (2026)

Reading about BOQ structure is one thing — seeing an actual filled-in sample makes the format click. Here’s a real, worked sample BOQ for a small construction project, with every column filled in so you can see exactly how quantity, rate, and amount connect.

Sample BOQ: Ground Floor Residential Unit (1,200 Sq Ft)

S.No Description Unit Qty Rate (₹) Amount (₹)
1 Excavation in foundation, ordinary soil Cum 38 195 7,410
2 PCC 1:4:8 below footing Cum 5.5 5,400 29,700
3 RCC M20 footing, column, plinth beam Cum 12 8,100 97,200
4 Brick masonry in CM 1:6, 230mm wall Cum 22 6,500 1,43,000
5 Internal + external plaster, 12mm Sqm 310 285 88,350
6 Vitrified tile flooring, 600x600mm Sqm 115 820 94,300
Subtotal 4,59,960

This is a partial sample — a real project BOQ would continue with doors/windows, painting, electrical, plumbing, and sanitary items before closing with an abstract of cost.

What Makes This Sample “Correct”

  • Every quantity ties back to a drawing dimension — nothing is a rounded guess.
  • Units follow standard convention — Cum for concrete/excavation, Sqm for area-based finishes.
  • Rates reflect the item’s actual scope — a plaster rate includes material and labour, not just cement cost.
  • Amount = Qty × Rate, consistently, with no shortcuts or estimates in the final column.

💡 Turn this sample into your own working file

Copying a static sample only gets you so far — the moment a quantity changes, you’re back to manual recalculation. Our Civil Work Estimate & BOQ Template has this exact structure pre-built with live formulas, so updating one number updates the whole sheet.

From Sample to Working File

Civil Work Estimate & BOQ Template — ₹249

Formula-linked, CPWD/DSR compliant, ready to fill with your own numbers

Browse All Templates →

Frequently Asked Questions

What does a real sample BOQ look like?
A table with item description, unit, quantity, rate, and amount for every construction item, grouped by section (earthwork, RCC, masonry, finishing) with subtotals and a final abstract of cost.

Is a sample BOQ the same for every project?
No — the structure (columns, sections) is similar, but the actual items, quantities, and rates change based on the project’s drawings and scope.

Can I use a sample BOQ as a template for my own project?
A static sample is useful as a reference, but a formula-linked template saves far more time since quantities and amounts recalculate automatically as you enter your project’s numbers.


Related: BOQ of Civil Work: Full Sample · BOQ Construction Project Example · Detailed BOQ for Construction

Share the Post:
Scroll to Top